Author: Joy Ramsey

Why the Lewis Water Park Must Be Stopped

See four City-documented reasons Fayetteville should stop the $92–$113 million water park at Lewis Fields before plans advance.
The Case Against Fayetteville’s Proposed Aquatic Center

Why the Lewis Water Park Must Be Stopped

Fayetteville plans to replace the Lewis Fields soccer complex with a $92–$113 million water park and aquatic center. The proposed site is in a FEMA flood zone, the financial plan depends on a permanent taxpayer subsidy, and residents were never asked whether Lewis Fields was the right location. The City’s own records show why this plan should not move forward.

Read the Four Reasons Take Action
$92M–$113MProjected construction cost
$350K–$400KAnnual taxpayer subsidy, competition pool alone
FEMA Zone AFederal flood-zone — CLOMR required
$2.6MHidden offsite costs not in the estimate
The Case in Brief

Four reasons Fayetteville should stop the Lewis water park plan

Documents obtained through the Freedom of Information Act reveal four interlocking problems. The evidence comes from the City’s own staff, engineers, consultants, and feasibility studies.

1

It’s financially unsustainable

The City’s own study admits facilities that cover their costs are “rare,” projects a permanent ~30% taxpayer subsidy, and shows the competition pool running a $350K–$400K annual deficit — on top of $10.8M in contingencies for soil that has never been tested.

2

The site is in a floodplain

Lewis Fields sits in FEMA Zone A, and Hamestring Creek begins inside the park. The City’s own 2021 study calls the flooding chronic and unfixable — caused by a “lack of topographic relief” that cannot be engineered away.

3

The selection process was flawed

The City’s own Parks Director wrote that consultants weren’t “putting any real effort into site selection.” The public was never asked about Lewis. It was chosen mainly because the City already owned the land — not because it was the best fit.

4

Comparable facilities raised serious warnings

City staff toured five aquatic centers and documented staffing shortfalls, flooding, corrosion, failed mechanical systems, cracked decking, and major water loss — the same kinds of risks Fayetteville would take on here.

1 — The Money

The cost is enormous, growing, and built on untested assumptions

An official $92 million — and the real number may be $113 million

The most recent official estimate puts the project at $92,175,349. A Parks Department memo costing all program elements together reaches $112,916,274. The estimate includes $10.8M in contingencies — and the soil under the site has never been tested.

“A geotechnical investigation has not yet been completed on the Lewis Park property. Unsuitable soil conditions, groundwater discovery, and rock excavation all have the potential to adversely impact the construction budget.”

— From the City’s internal aquatic center cost-estimate memo

A permanent subsidy is built into the plan

The City’s final feasibility study forecasts roughly 70% cost recovery — meaning 30% of operating costs must be subsidized by taxpayers forever. The competition pool alone is projected to recover only 40–45% of its costs.

“Facilities that can consistently cover all of their operating expenses with revenues are rare.”

— From the City’s final Aquatics Feasibility Study

The financial model was even built using an electricity rate of 5¢/kWh when the actual rate is 13¢/kWh — a 160% error discovered just weeks before key decisions.

A senior staffer raised the alarm — and was told to stay quiet

In December 2025, the City’s Park Planning Superintendent, Ted Jack, drafted a warning about the project’s financial risk, citing similar facilities that blew past their projected subsidies. His supervisor, Parks Director Alison Jumper, stopped him from sending it.

“Please hold on this. I’ve discussed with Keith this week and Admin is confident… I’d prefer you not send anything until after we can discuss.”

— Parks Director Alison Jumper, in an internal city email to Park Planning Superintendent Ted Jack, Dec. 5, 2025

His suppressed analysis warned that industry pro formas “often underestimate operational costs by 20–40%, particularly for staffing and utilities.” He also noted the City’s own feasibility study put the indoor facility’s first-year subsidy at $750,000, and that an indoor aquatic center is “generally, the most expensive park and recreation facility to build and operate, based on cost per use.”

$2.6 million in required offsite work isn’t even in the estimate

An internal email chain identifies costs the $92M figure leaves out:

Required offsite workPreliminary cost
Downstream sanitary sewer improvements$684,400
Lewis Avenue full reconstruction (1,350 ft)$1,214,828
Trail connections & pedestrian safety$739,191
Franchise utility relocation & right-of-wayNot yet calculated
Total (partial)$2,638,219+

— From an internal city email among Project Director Wade Abernathy, Public Works Director Chris Brown, and Parks Director Alison Jumper

2 — The Flooding

You cannot engineer away a flood zone

The land is in a federal flood zone — and the flooding is permanent

Lewis Fields is in FEMA Zone A. Hamestring Creek originates inside the park. The City’s 2021 drainage study found the flooding cannot be fixed because the land is simply too flat to drain.

“The flooding is primarily due to the lack of topographic relief within the developed portions of the Project area.”

— From the City’s 2021 Hamestring Creek drainage study (FTN Associates)

Building here requires federal approval — a Conditional Letter of Map Revision (CLOMR) from FEMA — a process that can take 12–24 months and may be denied. It is not currently reflected in the project schedule or budget.

Development will push more flooding onto neighbors

The City’s own Stormwater Manager confirmed that paving large impervious surfaces “increase[s] runoff” and that stormwater “flows downstream, potentially increasing localized flooding in adjacent neighborhoods.”

“What flood mitigation plan is in place to account for all the water displacement… Will it ultimately be forced down my street… making the flooding by my home way worse than it already is?”

— A nearby resident, in a letter to City officials

The City rejected another pool site for this exact reason

“The presence of a floodplain beneath the existing structure, combined with the complexity of obtaining approvals from federal and jurisdiction authorities, renders the site unsuitable for redevelopment.”

— From the City’s feasibility report, on why Wilson Park Pool was rejected

Lewis Fields carries the same FEMA Zone A designation and the same federal approval requirements — yet that logic was not applied when Lewis was chosen.

3 — The Process

The site was picked for convenience, not for the community

City staff didn’t trust the consultant’s own analysis

“They don’t seem to be putting any real effort into site selection… I’m still not satisfied with their analysis.”

— Internal city email between Recreation Program Manager Dean Rawlings and Parks Director Alison Jumper, Nov. 2024

This was written just two weeks before the consultant produced the matrix that recommended Lewis Fields — the basis for a $92 million bond decision.

Lewis won because the City already owned it

“Lewis Park scores the highest… as well as removing land acquisition cost.”

— From the City’s site-selection documentation

A flat, developable 103-acre alternative site was identified and passed over. On the consultant’s own objective scoring, Lewis only tied for the top spot — it pulled ahead solely on the partnership and land-cost-avoidance factors. The “savings” simply shift costs — displacing soccer fields and forcing the school district and community to absorb them.

The public justification was written to fit the decision

When it came time to explain the choice to the boards, the consultant told the City the rationale would have to be reverse-engineered to support Lewis:

“I believe this needs to be authored by the City… I think it would be more effective to clearly show how the parameters used to analyze the sites led to Lewis being the preferred site.”

— The City’s design consultant (Crafton Tull), in an internal email, Feb. 2026

The public was never asked about Lewis

Neither of the City’s two public surveys ever named Lewis Park or Wilson Park as candidate locations. The second survey was “restricted to focus on proposed concepts,” and the concept images “did not include or reflect location.” The Fayetteville School Board — which co-owns 12.3 of the park’s acres — was never formally consulted before the site was locked in.

4 — The Warnings

The City toured five comparable facilities. Here’s what they found.

In late 2025, a City team — including CFO Steve Dotson and Parks Director Alison Jumper — toured comparable aquatic facilities. Their own tour notes document a pattern of failures.

FacilityProblem documented by City staff
Rogers, ARPlanned for 25 lifeguards; operations actually require 100 — a 4× staffing miss.
Republic, MOStormwater runoff floods the facility’s ground-level pumps; added third-party weekend security.
Blue Springs, MOSignificant chlorine smell and humidity; corrosion from inadequate HVAC.
Conway, ARChemical-feed system design flaws — undersized pipes replaced after opening; outdoor decking already cracking.
Lenexa, KSLosing significant water from slide runoff due to inadequate drains and recirculation.

The City’s 40-question site-visit framework — which CFO Steve Dotson personally expanded with pointed finance questions — ended every interview with a telling final question: “Would you do this again if you had the choice?”

What’s at Stake

What Fayetteville loses

  • The soccer fields. Lewis Fields serves Fayetteville youth leagues. The facility and its 492-stall parking lot need a 7.44-acre minimum — nearly the entire 8.5 acres the City controls at Lewis, spilling onto school-district fields.
  • Permeable green space. Open land that today absorbs water will become impervious concrete — adding to the downstream flood burden.
  • Wildlife habitat. An AGFC Stream Team leader noted “endangered birds in the tree canopy”; residents report a large bat population feeding along the creek. No habitat assessment appears in the record.
  • A vulnerable neighborhood’s stability. The park abuts Washington Plaza public housing and serves families near Asbell Elementary — raising real concerns about amenity-driven displacement that the City has not addressed.
See For Yourself

Read the source documents

Every claim on this page comes from official City of Fayetteville records obtained through the Freedom of Information Act. Don’t take our word for it — read them in full:

Help Stop the Lewis Water Park

This decision is not final. Sign the petition to preserve Lewis Park and stop the proposed aquatic center, then help more Fayetteville residents see the evidence before the soccer fields and green space are paved over.

Sign the Petition Get Involved / Contact Us Follow on Facebook

Every claim on this page is sourced from official City of Fayetteville records obtained through the Freedom of Information Act. No outside sources have been added; quotations are verbatim excerpts from City documents.

Take Action

April 2026

The March 3 Bond package passed, however there was significant voter opposition to the specific Aquatic/Rec Center Question #8 for $61.9 Million dollars. That particular bond narrowly passed by a 218 vote difference out of 14,896 votes cast, 50.7% for and 49.3% against the measure. This razor thin margin shows many citizens are concerned with construction on the preferred location of Lewis Park and with the overall capital infrastructure and long-term operating costs.
We will remain engaged and involved moving forward in the planning of the proposed facility by contacting and attending meetings of our City Council, City Administration, Parks and Rec, Fayetteville Public School Board, Parks Advisory Board, Planning Commision, and with individuals who are interested in finding a solution and a location for the Aquatic and Recreation Center that facilitates the need for indoor swimming without sacrificing our beloved and needed greenspace and multiple-sport field complex at Lewis Park.

Below is the link to the #8 Vote Result Precinct Map, which illustrates where the for/against votes were. This map is important to see and share as the neighborhood around Lewis Park is definitively against losing this vital community park that functions not only as a sport fields and gathering space, but also as a floodplain and stormwater absorption systems working to capture, slow, and spread runoff into the ground, reducing flooding and improving water quality in the Hamestring Creek Headwaters.

https://imaginative-lily-ccc968.netlify.app/

VOTE No Bond Q#8 -March 3

VOTE No Bond Q#8 -March 3

We are asking for your support to Save Lewis Park by voting NO to the $61.9 Million Aquatic Center Bond Issue #8, March 3, 2026.

The current aquatic recreation center plan is incomplete, with references to amenities that “may be included.” What is certain is the preferred location of Lewis Park will destroy 4 full sized soccer fields that serve multiple sports. Lewis Park is more than fields, it is a needed vital green space in a residential neighborhood that mitigates stormwater and slows runoff to Hamestring Creek.

The feasibility study estimated operating cost of $2 Million annually, with estimated shortfall of $700,000 +every year, after fees and donations. Many other civic services and salaries could be funded with this amount of our taxpayer money.

The Study: The $151,591 June 2024 – September 2025 aquatic feasibility study selected Lewis Park, at Mount Comfort Road and Lewis Ave., as the preferred site, without recognizing the loss of essential and heavily used multi sport fields being sacrificed at this location. The costs of replacing these fields is not analyzed or included. Building at Lewis will trigger another another major project to purchase and build another field complex. Recommendations from the feasibility study are: Improvements to Wilson Park pool, Multiple outdoor pools, Partnerships with other organizations to manage aquatic facilities.
https://www.fayetteville-ar.gov/DocumentCenter/View/38649


Bond Vote: October 21, 2025, the City Council voted 6-2 to approve the ballot language and set the date for a bond referendum with nine issues. Residents will vote on each issue individually, per state law.


Contracts: November 4, 2025, the City Council Council members voted 5-3 to approve two separate items related to work on a proposed aquatics center at Lewis Park. The two contracts combine for a total of $272,523. One of the items was a $232,524 architectural contract with local firm Crafton Tull. The other was a $39,999 construction manager contract with local firm CDI Contractors.
https://fayettevilleflyer.com/2025/11/05/fayetteville-council-approves-contracts-for-preliminary-work-on-proposed-aquatics-center/


Why Help Save Lewis Park

Why Help Save Lewis Park

Vote No Bond Q#8 = $61.9 Million Aquatic Center
Preferred site from feasibility study is Lewis Park. We save the park by making the city rethink their plans to destroy 4/6 full sized fields. These fields are vital, central, and needed. Please ask the city to consider other options suggested in their study.

Preserve Lewis Park, Build Aquatic Center Elsewhere

Preserve Lewis Park, Build Aquatic Center Elsewhere

The plans to build a proposed Aquatic Center at Lewis Park will decimate the existing fields, reducing quantity, size, and flexibility of this park. Addition of asphalt for parking and rooftops for the indoor pool and peripheral buildings, lazy river, slides and other features, will have detrimental impact on the areas ability to mitigate stormwater. Increased traffic will negatively impact the walkability and safety of the residential neighborhood. This proposed Aquatic Center will cost from $61- $107 Million dollars, which will be presented in the bond issue to be voted on in March of 2026.

Please support us in asking the City Council, Parks Department, and Mayor to find another location for this planned project rather than destroying this multipurpose, central, essential, neighborhood park. Logic would dictate maintaining Lewis Park over trying to replace what would be lost.